Planning production orders brings together data from all over MKG, such as operations and resources, but also employees and time registration. If an operation goes differently than planned, a notification may arise. What does such a notification mean and what triggers it? This article provides an overview of all planning notifications.
- MKG5
An order is automatically planned forward when no delivery date is entered. The end date is calculated based on the number of days from today during which planning is not allowed—according to the administration setting 'For planning ahead, start planning after'—plus the lead time in the schedule.